Planning guide · 12 min read
First-Time Exhibitor
Checklist
A week-by-week plan from signing the space contract through delivery at the venue, every deadline, order form and decision that catches first-time exhibitors, in the order it hits.
The short version
This checklist starts at week 16, a comfortable standard plan. Work backwards: design and the booth contract lock by about week 7, production runs from week 6 to week 1, advance service orders before the discount deadline, and delivery to the venue by week 1. Portables and Rescue Booth Builds in as little as 2 weeks. Standard lead time for all items is 3 months. Large custom builds: 4 months or more recommended. Starting inside week 13 is a rush. Budget the booth at 40 to 50% of total show cost, space, services, travel and staffing consume the rest.
Budget the whole show, not the booth
First-time exhibitors almost always budget the booth and treat everything else as incidental. In reality the booth is under half the number. Building the full picture before you commit prevents the mid-project scramble where graphics get cut to pay for electrical.
| Line item | Share of total | Notes |
|---|---|---|
| Floor space | 20 to 30% | Priced per sq ft; corners and islands cost more |
| Booth (rental or build) | 25 to 35% | The part everyone budgets |
| Show services | 15 to 25% | Electrical, rigging, cleaning, internet, furniture |
| Travel & accommodation | 10 to 20% | Show-week hotel rates are punitive, book early |
| Staffing & training | 5 to 10% | Time cost of the people on the floor |
| Marketing & follow-up | 5 to 10% | Pre-show outreach, giveaways, lead retrieval, post-show sequence |
Weeks 16 to 12: foundation
Everything downstream depends on decisions made here.
- ▸Sign the space contract and confirm your booth number and neighbours
- ▸Download and actually read the exhibitor manual, note every deadline in a shared calendar
- ▸Confirm display rules for your booth type: height limits, hanging-sign eligibility, sightline restrictions
- ▸Define one measurable objective for the show (qualified meetings, demos booked, pipeline value)
- ▸Set the full budget using the table above
- ▸Brief your exhibit partner and request 3D concepts
Weeks 12 to 8: design
Concepts are still in motion. Approval and the contract come next, by about week 7.
- ▸Review 3D concepts and the floor plan, including electrical drop locations
- ▸Finalise messaging hierarchy, the backwall headline must be legible from 20 feet
- ▸Order lead retrieval units
- ▸Book hotels and flights before show-week rates escalate
- ▸Start pre-show outreach: book meetings into the calendar now, not on the floor
About week 7: design and contract lock
On a standard build, design and the contract lock by about week 7 so production can run from week 6 to week 1. A larger custom build needs eight to twelve weeks of production, so that lock happens earlier, on a plan that starts about 22 to 26 weeks out.
- ▸Approve the 3D design and floor plan, including the exact electrical drop locations
- ▸Lock the booth contract so production can be scheduled
- ▸If the build is larger, start the plan about 22 to 26 weeks out so production has eight to twelve weeks
Weeks 6 to 4: advance service orders
The advance-order discount deadline usually falls four to six weeks before move-in, inside the production window. Missing it costs 20 to 35% on services for no benefit whatsoever.
- ▸Submit all advance service orders: electrical, rigging, internet, cleaning, furniture, labour
- ▸Confirm rigging approval and dead-load certification if you have a hanging sign
- ▸Approve print-ready graphics files
- ▸File your Exhibitor Appointed Contractor notice and insurance certificates if using a non-official installer
- ▸Book and badge install crews
- ▸Confirm delivery to the venue and the target move-in time
Weeks 6 to 1: production and delivery
Standard production runs week 6 to week 1. Fabrication completes and the booth is prepared for delivery to the venue. Your attention shifts to the people and the follow-up.
- ▸Fabrication and graphics complete; review photos of the set build if offered
- ▸The booth is delivered to the venue for your move-in window
- ▸Run booth staff training: opening question, qualification criteria, demo flow, handoff
- ▸Build the post-show follow-up sequence before you travel, it never gets written afterwards
- ▸Source literature, giveaways and consumables locally where possible
- ▸Confirm on-site contacts and mobile numbers for every vendor
Show week and after
Arrive for install, not for opening. Walk the space with your project manager, confirm the electrical drop is where the drawing said, and test every screen before the hall opens.
The follow-up window matters more than anything that happens in the booth. Leads contacted within 48 hours convert at a multiple of those contacted the following week, which is why the sequence gets written before you fly, not after.
- ▸Attend install day and sign off the completed build
- ▸Brief staff each morning; rotate them off the floor every two hours
- ▸Capture leads digitally with qualification notes, not just a badge scan
- ▸Photograph the finished booth for next year's brief and internal reporting
- ▸Confirm dismantle timing and empty-crate labels before teardown
- ▸Send follow-up within 48 hours; hold a debrief within two weeks while detail is fresh
FAQ
Questions we get on this
How much does it cost to exhibit at a trade show for the first time?+
A first-time 10×10 rental is starting from $16,250 USD, and a 10×20 rental is starting from $19,500 USD. Floor space, travel and staffing are separate from the booth.
How far in advance should I plan a trade show?+
Portables and Rescue Booth Builds in as little as 2 weeks. Standard lead time for all items is 3 months. Large custom builds: 4 months or more recommended. The advance-order discount deadline usually falls four to six weeks before move-in.
What do first-time exhibitors most often get wrong?+
Three things: budgeting only the booth and being blindsided by show services, missing the advance-order discount deadline, and writing the follow-up plan after the show instead of before it.
Should a first-time exhibitor rent or buy a booth?+
Rent. You don't yet know which footprint, layout or messaging works for your audience, and a rental lets you learn that without capital risk. Buy only once you have a proven format and a five-plus-show annual calendar.
Keep reading
Other exhibitor guides
Shipping and Union Labour
We ship the booth to the advance warehouse or direct to the hall, then install it on your move-in window. Shipping and delivery are included. In union…
On-site guideDelivery and Install in Canada and the USA
Traction X delivers the booth to the venue and installs it on your move-in window in Canada and the United States. Dismantle is included. A project ma…
ReferenceTrade Show Exhibit Glossary
Every term on your show-services order form, defined in plain language.
Get a quote in 1 hour
Preliminary quote within 1 hour. Detailed quote within 24 hours. Portables and Rescue Booth Builds in as little as 2 weeks. Standard lead time for all items is 3 months. Large custom builds: 4 months or more recommended.
10-minute call for projects of $10,000 USD and up. 30-minute design strategy session for projects of $30,000 USD and up.
Want us to run the logistics instead?
Anything you see online is a starting range only. Send us your show, footprint and dates. Preliminary quote within 1 hour. Detailed quote within 24 hours. Portables and Rescue Booth Builds in as little as 2 weeks. Standard lead time for all items is 3 months. Large custom builds: 4 months or more recommended.