Week 16 to 13: standard start
Portables and Rescue Booth Builds in as little as 2 weeks. Standard lead time for all items is 3 months. Large custom builds: 4 months or more recommended.
Kickoff covers your objectives, budget band and brand assets, and you confirm the booth number and the result you want from the show.
Week 12 to 8: design
Concept and floor plan options arrive in this window. It is still the cheapest time to change the layout.
About week 7: drawings, long-lead items and the contract
On a standard build, you approve the design and lock the booth contract by about week 7. That leaves production running from week 6 to week 1. The approved production package is signed. Long-lead items are ordered, including custom millwork, LED walls with a specific pitch, and hanging structures that need permit drawings. Show-services forms go in before the early-bird cutoff.
Week 6 to 1: production
Standard production runs week 6 to week 1. The booth is built, photographed and checked in the shop. Graphics are printed. Delivery to the venue is scheduled.
A larger custom build stays in production for eight to twelve weeks, which is why that plan starts about 22 to 26 weeks out.
Week 3 to 1: delivery to the venue
Delivery to the venue is confirmed while production finishes. The on-site project manager is confirmed. Final show-day timing is sent to your team.
Show week & post-show
Install, show, dismantle. Post-show debrief with photos and an asset check inside 10 business days.
Inside week 13: a rush, including a 4-week rescue
Starting inside week 13 is a rush, not a standard build. A 4-week rescue skips a ground-up design, starts from an existing modular chassis, and layers custom graphics plus one hero millwork counter. We still deliver and install at the venue. Call us the day you know the show date.